Construction of infrastructure facilities of the “National Industrial Petrochemical Technopark” special economic zone in Atyrau region (Karabatan and Tengiz sections). The project “External power supply”

  • Object:
    Construction of infrastructure facilities of the “National Industrial Petrochemical Technopark” special economic zone in Atyrau region (Karabatan and Tengiz sections). The project “External power supply”
  • Customer:
    Karabatan Utility Solutions LLP
  • Developer:
    Bazis Construction LLP
  • Start date:
  • Completion date:

Project information

Minimization of the cost of construction within the framework of project documentation and current building regulations, provided that a quantitative and qualitative workable result is achieved.

Technical and economic indicators

  • Two new 220kV overhead lines (OL) from 220/110/10kV NIPT SEZ to 220/110/10kV Atyrau, right chain is 41.12km, left chain is 41.24km
  • A new 220/110/10 kV SS of NIPT SEZ with two autotransformers with a capacity of 250MVA, being built on the territory of the “National Industrial Petrochemical Technopark” special economic zone
  • Expansion and reconstruction of the existing OSG-220kV of 220/110/35/10kV Atyrau SS for two linear cells
  • Two 110kV cable lines (CL) from the 110kV GIS on the territory of the COSAG to the new substation (SS) 220/110/10kV of NIPT SEZ