Object:Construction of infrastructure facilities of the “National Industrial Petrochemical Technopark” special economic zone in Atyrau region (Karabatan and Tengiz sections). The project “Construction of the on-site highway”
-
Customer:Karabatan Utility Solutions LLP
-
Developer:Bazis Construction LLP
-
Start date:
-
Completion date:
Project information
The construction of the road is intended to service the construction and operation of the petrochemical complex under construction.
Technical and economic indicators
- Project category on-site III-B category
- Nature of construction – new construction
- The length of the highway, taking into account the exits, is 2.8 km
- The width of the roadway is 7.5 m
- Type of road topping is capital
- The standard duration of road construction is 9 months
- Abutments III-B category 3 pcs.
- Road signs 34 pcs