Construction of infrastructure facilities of the “National Industrial Petrochemical Technopark” special economic zone in Atyrau region (Karabatan and Tengiz sections). The project “Construction of the on-site highway”

  • Object:
    Construction of infrastructure facilities of the “National Industrial Petrochemical Technopark” special economic zone in Atyrau region (Karabatan and Tengiz sections). The project “Construction of the on-site highway”
  • Customer:
    Karabatan Utility Solutions LLP
  • Developer:
    Bazis Construction LLP
  • Start date:
  • Completion date:

Project information

The construction of the road is intended to service the construction and operation of the petrochemical complex under construction.

Technical and economic indicators

  • Project category on-site III-B category
  • Nature of construction – new construction
  • The length of the highway, taking into account the exits, is 2.8 km
  • The width of the roadway is 7.5 m
  • Type of road topping is capital
  • The standard duration of road construction is 9 months
  • Abutments III-B category 3 pcs.
  • Road signs 34 pcs