Construction of infrastructure facilities of the “National Industrial Petrochemical Technopark” special economic zone in Atyrau region (Karabatan and Tengiz sections). The project “Water treatment”

  • Object:
    Construction of infrastructure facilities of the “National Industrial Petrochemical Technopark” special economic zone in Atyrau region (Karabatan and Tengiz sections). The project “Water treatment”
  • Customer:
    Karabatan Utility Solutions LLP
  • Developer:
    Bazis Construction LLP
  • Start date:
  • Completion date:

Project information

Providing participants of the “National Industrial Petrochemical Technopark” special economic zone with industrial, fire-fighting, desalinated and demineralized water. Cleaning of household, industrial stormwater and chemically contaminated wastewater.

Technical and economic indicators

The main components of the project:

  • 31 km long river water conduit
  • Industrial fire-fighting water 650 m3/day
  • Desalinated water 9120 m3/day
  • Demineralized water 1422 m3/day
  • Wastewater treatment (chemically contaminated, oily, stormwater and household) 9426 m3/day
  • The objects of engineering support of the GTPP and the corridor of engineering networks
  • Installation of water treatment and wastewater treatment networks